Difference between revisions of "MainPage:Nuclear:KaonDetector:AerogelDetectorConstruction"
Jump to navigation
Jump to search
Line 28: | Line 28: | ||
== Checklist of the progress on the milling == | == Checklist of the progress on the milling == | ||
− | The following | + | The following checklists are an overview of the main parts of the detector and the progress on its construction. As it is going to be constructed one diffusion box and three aerogel trays, these list provide the status on the progress for each piece of all of the items. |
+ | |||
+ | Last update: October 21, 2011 | ||
{| style="text-align: center; color:black; background: #efefef; border: 1px solid blue;" cellpadding="4" cellspacing="0" border="0" | {| style="text-align: center; color:black; background: #efefef; border: 1px solid blue;" cellpadding="4" cellspacing="0" border="0" |
Revision as of 09:22, 21 October 2011
This page is under construction. It requires a review! |
⇐ Back to the Kaon Detector page |
Drawings
Links to drawings files.
Material orders
The materials had been ordered by Dr. Marek. Almost all the structural pieces (aluminum pieces) was delivered on October 10th, at CUA. Paul started milling the first piece of our new detector on October 13!
Checklist of the progress on the milling
The following checklists are an overview of the main parts of the detector and the progress on its construction. As it is going to be constructed one diffusion box and three aerogel trays, these list provide the status on the progress for each piece of all of the items.
Last update: October 21, 2011
(Legend: is ready,
is being milled at the moment and
is not milled)
It is going to be constructed three trays (aerogel boxes). The following list includes the milling parts required for all of these trays.